It's been a while since I've updated this, and the house is coming along nicely.
Day 10 The cement forms are removed.

Day 11 The basement walls are waterproofed
Day 12 The foundation has been backfilled and gravel layed in the basement and garage
Day 17 The basment and garage floor cement has been poured
Day 24 (after a week of rain) The sill plate the lower level floor are in place
Day 25 Now the walls start going up.
Day 29 The garage is finished and the second level floor joinst go in.
Day 30 Starting the second floor walls
Day 31 Second floor walls are up, and the morning room roof is framed